DIGET Business Case · LNG Liquefaction
Train 2: one night on the Gulf Coast
Four things go wrong on one liquefaction train between midnight and dawn. What DIGET does about each of them.
Why this case matters
A tripped train does not simply restart: it was down about 5 to 10 hours in reported trips, with flaring, and cooldown uses a third to a half of a day's production. One trip costs about $4–6M of output at $10/MMBtu and $12–19M at spot. The causes are rarely dramatic: a single pressure transmitter, an anti-surge valve that went wide open, a valve malfunction.
Simulation results · Round 3
Detects the failure, reconstructs what is really happening, reconfigures the train, checks the result, and when it can't be held, says so and stops it in order.
Unplanned trips
244 → 85
recoverable faults; 159 avoided, none added
First corrective action
6 s
median; conventional about 4 minutes
More on-spec LNG
+14%
in the 20 minutes after a fault
Impossible cases
320/320
declared; 172 stopped in order instead of tripped
4,140 paired runs on new seeds, 69 fault scenarios. Safety events: 336 vs 2,440 (−86%).
The night, minute by minute
00:40
Full rate
A trip signal from refrigerant compressor A flickers for one second. The compressor never stopped. The automatic runback reacts anyway and starts cutting the train to 50%.
Checks, then ignores it
Compares the signal with the compressor's own flow and power: it is still running. No runback, no lost output. Left alone in 60 of 60 tests; the conventional runback cost about 40% of output.
02:15
Full rate
The control transmitter for LNG temperature starts to drift. It reads colder than the truth, so the control system lets product warm toward off-spec.
Reconstructs · reroutes
Cross-checks it against the three safety transmitters, flags it, and moves the control loop onto healthy ones (median 2 min). Conventional: median 9.6 min to switch.
03:47
No alarm yet
The gas turbine driving compressor A loses 30% of its power. There is no trip signal. Refrigeration falls short and the heat exchanger begins to warm.
Detects & reconfigures · 13 s
Sees flow fall against speed, marks compressor A at about 70%, recomputes what the train can still make, cuts the feed to that rate and re-sizes the expansion valves.
03:50
Two failures
Three minutes later, the belt on air-cooler fan bank 1 breaks. Condensing capacity drops and discharge pressure climbs toward the trip limit.
Reconstructs & reconfigures again
Sees fan motor current fall, adds the lost fan bank to its picture and trims the rate again. Train kept running in 60 of 60 tests; the conventional plant tripped in 19 of 60.
—
The other branch
Had compressor A tripped outright and compressor B then lost half its power, no control system could keep the train running.
Protects · stops in order
Within 13 seconds (median) it states the shortfall cannot be covered and brings the train down in order: a controlled stop, plant in a known state, restart planned, in 60 of 60 tests; conventional tripped in 60 of 60.
06:00
Shift change
Train 2 is still making on-spec LNG at about 90% of design rate. No trip, no restart, no cooldown.
Record
The day shift gets a list: compressor A turbine at ~70%, fan bank 1 belt, LNG temperature transmitter drifting. Every decision is logged with its evidence.
Without DIGET
A false signal halves output for minutes. A drifting instrument steers the train for nearly ten minutes. A turbine losing power and a broken fan belt arrive while two operators read alarms, and in about a third of cases the train trips. Restart and cooldown cost most of a day.
With DIGET
Each fault is identified in seconds, the train is rebuilt around it, and production carries on at what the remaining equipment can safely carry. Operators get a plain statement of what failed and what is compensating, including when it can't be saved.
Schematic · the train, fault by fault
Walk the night, one block at a time
Schematic · the train, fault by fault
One night on Train 2, one box at a time
Each block is a part of the train; colours show the state DIGET is holding. The picture is qualitative: no model internals, parameters or equations are shown.
Swipe the diagram sideways
Train output
design rate
- Running as normal
- Working at its limit
- Drifting, not trusted
- Failed
- Out of service
00:40 · a false trip signal
1 / 5
A trip signal from refrigerant compressor A flickers for one second; the machine never stopped. DIGET compares it with the compressor's own flow and power, finds it running, and does nothing. The conventional automatic runback would have started cutting the train.
Illustrative schematic. Measured simulation results are in the tables on this page.
Not an alarm. Not predictive maintenance.
| Question | Alarms & DCS | Predictive maintenance | DIGET |
|---|---|---|---|
| When does it act? | When a limit is crossed | Days or weeks before a predicted failure | In the first seconds after a failure |
| A transmitter fails | The loop follows it; operator must notice | Not covered | Flags it and moves the loop onto healthy measurements |
| A compressor loses power | Operator cuts rate in 10% steps | May have flagged wear, does not act | Reconstructs how much is left and sets the train to it |
| A false trip signal | Automatic 50% runback | Not covered | Confirms the machine is running and ignores it |
| Touches the safety system? | — | — | Never. It works through the control system, inside every trip limit. |
Where DIGET sits
The missing layer between maintenance and the safety system
| Layer | What it does | Timescale | Where DIGET fits |
|---|---|---|---|
| Planning & reliability | Forecasts wear, models the plant as designed | Days to months | Feeds them: every fault is logged with evidence |
| Optimisation (APC) | Pushes the train toward profitable limits | Minutes | Gives it a true plant: real capacity, trustworthy measurements |
| DIGET | After a failure: works out what broke, rebuilds the picture, re-runs on what is left, or stops in order | Seconds | The missing layer |
| Basic control (DCS) | Holds set points; raises alarms | Under a second | DIGET acts only through it |
| Safety (SIS) | Trips the train at a limit | Under a second | Never touched |
| Field | Instruments, compressors, fans, valves | — | Reads existing instruments; no new hardware |
In one line: predictive maintenance works before the failure, the safety system acts at the limit, and DIGET works in the seconds between.
Three-round scorecard
Same gates every round, new seeds every round. Code sealed before each run. Round 3 counts as not yet demonstrated: the safety gate came in at 99.35% against 99.5%.
| Gate | Bar | Round 1 | Round 2 | Round 3 (all 69) | Round 3, 16 new only |
|---|---|---|---|---|---|
| G1 Ride-through | ≥ 95% | 97.5% | 97.5% | 97.3% | 96.8% |
| G2 Production | ≥ 95% | 98.7% | 98.7% | 99.1% | 99.7% |
| G3 Safety | ≥ 99.5% | 97.7% | 99.6% | 99.35% | 98.2% |
| G4 Impossible declared | ≥ 99% | 100% | 100% | 100% | 100% |
| G5 False refusal | < 5% | 0.0% | 0.0% | 0.0% | 0.0% |
| G6 Glitches ignored | ≥ 99% | 100% | 100% | 100% | 100% |
| G7 Right part · never healthy | ≥ 95% · ≥ 99.5% | 100% · 100% | 100% · 100% | 100% · 99.6% | 100% · 98.2% |
| G8 Capacity rebuilt | ≥ 90% | 94.6% | 94.6% | 96.5% | 100% |
| Gates passed | 7 of 8 | 8 of 8 | 7 of 8 | 6 of 8 (report only) |
The misses came from two new two-fault cases: a stuck suction-pressure transmitter followed by a compressor losing 60% of its power, and a stuck-open anti-surge valve followed by two lost fan banks, where DIGET misread the valve as a weak compressor. Round 4 targets exactly these.
DIGET in the plant
Three kinds of site, one product
| Fully equipped | Partly equipped | Basic | |
|---|---|---|---|
| Typical site | Large refinery, LNG train, petrochemical complex | Older refinery unit, chemical plant, mid-size gas plant | Gas processing plant, compressor station |
| Where DIGET connects | Between APC and DCS | On the DCS, beside the historian | On an edge computer linked to the PLCs |
| Tier | Closed-loop on critical units | Advisory first; closed-loop on key loops | Advisory; closed-loop where approved |
Refinery · FCC wet gas compressor
At 2 a.m. a suction pressure transmitter drifts low. Without DIGET the compressor surges and trips, the FCC goes to standby and the refinery is upset for 4–8 hours. With DIGET the true pressure is rebuilt every cycle in under 5 ms and APC stays on.
Partly equipped · crude heater
A pass flow transmitter fails low and starves the other passes, risking tube coking. DIGET rebuilds the true flow from outlet temperature, pressure drop and valve position. Avoiding coked tubes avoids a multi-day decoking outage worth millions.
Basic · gas plant separator
A stuck level transmitter closes the outlet valve until the safety system shuts in the plant: 6–12 hours of restart. On an edge computer DIGET rebuilds the true level and tells the operator, or holds the level itself.
How a site goes live
| Step | What happens | Time |
|---|---|---|
| 1 · Readiness assessment | Map instruments, failure history and the cost of each upset; pick the loops where DIGET pays first | 90–120 days, paid |
| 2 · Advisory | Read-only beside operators; every detection and rebuilt value scored against what happened | 3–6 months |
| 3 · Closed-loop | Approved envelope, management of change, hazard review | After site approval |
| 4 · Expand | More units, then other sites under an enterprise license | Ongoing |
Which use case to lead with
Recommendation: lead with LNG
| LNG liquefaction | Refinery | Hyperscale data centre | |
|---|---|---|---|
| Cost of one bad event | $4–19M per train trip | $1–10M+ per day of downtime | 1 in 5 major outages cost over $1M |
| Fit with DIGET | Very high | High, but dozens of units each needing a model | Medium: cooling is the fit |
| Evidence so far | Three simulation rounds | None yet; same engine | None yet |
| Path to a pilot | Test on the plant's own dynamic model, then advisory mode | Pick one unit, same path | Cooling-plant pilot |
A reduced-order model of one generic C3MR-style train, not plant evidence. A reference implementation, not the production engine; DIGET's internal model was deliberately given 8% gain errors. Next: Round 4, then a run against an operator's own dynamic plant model, shadow mode, one train, then fleet.